📐 Section 1 — Structural Plan Check Items (15 Points)

#Checklist ItemCode ReferenceStatus
S-01ASCE 7-16 wind speed map value confirmed for project addressASCE 7-16 §26.5REQUIRED
S-02Exposure Category (B, C, or D) determined and documentedASCE 7-16 §26.7REQUIRED
S-03Wind velocity pressure (qz) calculated: qz = 0.00256 × Kz × Kzt × Kd × V²ASCE 7-16 Eq. 27.3-1REQUIRED
S-04Ground Snow Load (Pg) from ASCE 7 snow map confirmedASCE 7-16 §7.2IF APPLICABLE
S-05Roof dead load capacity confirmed (min. 3 psf additional for panels)IBC 2021 §1606REQUIRED
S-06Roof framing member size, species, and grade documentedAWC NDSREQUIRED
S-07Rafter span table lookup or span calculation includedAWC Span TablesREQUIRED
S-08Lag bolt withdrawal capacity ≥ calculated wind uplift per attachmentAWC NDS §11.2REQUIRED
S-09Lag bolt embedment depth ≥ 2.5 inches into framing memberIBC / AHJ StandardREQUIRED
S-10Attachment spacing confirmed (max 48" on-center typical)Manufacturer + AHJREQUIRED
S-11Roof slope and panel tilt angle documentedAHJ Plan CheckREQUIRED
S-12Roof material type (composition, tile, metal) confirmed with mount systemManufacturer ApprovalREQUIRED
S-13Structural P.E. wet or digital stamp applied to all structural sheetsState Eng. ActREQUIRED
S-14Roof access pathway (3ft min.) to ridge or eave shown on layout planIFC §605.11REQUIRED
S-15Panel setback from roof edge (min. 18") shown on planIFC §605.11.1REQUIRED

⚡ Section 2 — Electrical Plan Check Items (20 Points)

#Checklist ItemCode ReferenceStatus
E-01DC conductor ampacity sized at 1.5625 × Isc (NEC 690.8 continuous duty)NEC 690.8(A)REQUIRED
E-02Temperature and conduit fill derating factors applied to conductor ampacityNEC 310.15REQUIRED
E-03120% Busbar Rule checked: (Panel Bus Rating × 120%) − Main Breaker ≥ Solar BreakerNEC 705.12(B)(2)REQUIRED
E-04AC disconnect switch shown within sight of utility meter and inverterNEC 690.13REQUIRED
E-05Rapid Shutdown initiator shown at main service panel or meterNEC 690.12REQUIRED
E-06Rapid Shutdown boundary labeled on roof plan (1ft from roof edge)NEC 690.12(B)(2)REQUIRED
E-07Single Line Diagram (SLD) included with all components labeledNEC 690 / AHJREQUIRED
E-08Module model, Voc, Isc, Vmp, Imp, Pmax labeled on SLDNEC 690.56REQUIRED
E-09Inverter model, max input voltage, max output current labeled on SLDNEC 690.56REQUIRED
E-10Grounding electrode conductor (GEC) shown from inverter to earth groundNEC 250.64REQUIRED
E-11Conduit type and size labeled on all runs (roof, attic, exterior)NEC 358/352/344REQUIRED
E-12Wire gauge labeled on all circuit conductors on SLDNEC 690REQUIRED
E-13String configuration (modules per string × strings in parallel) shownNEC 690 / AHJREQUIRED
E-14Maximum system voltage calculated: Voc × temperature correction factorNEC 690.7REQUIRED
E-15Utility interconnection POI (Point of Interconnection) labeled on SLDNEC 705.12REQUIRED
E-16Electrical P.E. wet or digital stamp applied to electrical sheetsState Eng. ActREQUIRED
E-17Battery system NFPA 855 energy limits checked (80kWh per control area)NFPA 855 §15IF BATTERY
E-18Battery disconnect and overcurrent protection shown on SLDNEC 706.15IF BATTERY
E-19MPU (Main Panel Upgrade) details included if bus rating insufficientNEC 705.12IF APPLICABLE
E-20Arc-fault circuit protection (AFCI) shown for DC circuits >80VNEC 690.11REQUIRED

🏛️ Section 3 — AHJ Administrative Items (12 Points)

#Checklist ItemNotesStatus
A-01Permit application form completed with correct APN / parcel numberCounty AssessorREQUIRED
A-02Title block on each sheet: project address, date, sheet number, revisionAHJ StandardREQUIRED
A-03Contractor license number and classification on title blockState Contractor LawREQUIRED
A-04Site plan (plot plan) showing property lines and panel location on roofAHJ Plan CheckREQUIRED
A-05North arrow and scale bar on all plan view drawingsAHJ StandardREQUIRED
A-06Utility company interconnection application submitted separatelyUtility TariffREQUIRED
A-07Equipment cut sheets (spec sheets) attached for all major equipmentAHJ Plan CheckREQUIRED
A-08Roof plan showing all panels with array dimensions and setbacks dimensionedIFC 605.11REQUIRED
A-09Warning labels list (DC, RAPID SHUTDOWN, DUAL POWER) per NEC 690.56NEC 690.56(C)REQUIRED
A-10HOA approval letter obtained if applicableCA Civil Code §714IF APPLICABLE
A-11Historical district review approval if applicableLocal OrdinanceIF APPLICABLE
A-12Plan set printed to correct scale (1/4" = 1' or 1/8" = 1' for large roofs)AHJ StandardREQUIRED

Need a P.E.-Stamped Plan Set That Passes First Time?

Our licensed engineers handle every item on this checklist — structural calculations, SLDs, rapid shutdown compliance, and AHJ coordination — with a 24-48 hour turnaround.